Section 1 · Kitchen Remodeling

A 12-Week Kitchen Remodel Plan You Can Actually Hand to Your Contractor

8 min read · Brooklyn, NY

GN

By Joseph Ng

Co-Owner & Lead Estimator, Creative Home Decor

Written from real Brooklyn job notes. 15+ years on Utica Ave. · 8 min read

Most kitchen remodel timelines online are sales documents. This is the one we hand contractors, with the same buffer weeks we use ourselves. 12 weeks is generous on purpose, it absorbs one bad inspection week and one freight delay without slipping the move-in.

Key Takeaways

  • Weeks 1 to 4 are planning, sample selection and orders, no demo yet.
  • Weeks 5 to 9 are the actual build.
  • Weeks 10 to 12 are finish, punch list, and your real life moving back in.
  • Two of the 12 weeks are buffer, do not use them up in week 1.
  • Hand this to your contractor before signing, not after.

Contractor Insight

If a contractor pushes back on a 12-week schedule for a full gut, ask them to show the cabinet lead time, the stone install date, and the inspection slot in writing. Most slippage is one of those three.

Brooklyn-specific calendar items

Holiday weeks the trades disappear: Memorial Day, July 4 week, Labor Day, Thanksgiving Thursday and Friday, and the entire week between Christmas and New Year. If your move-in date is January 5, the realistic install window is October 1, not December 1.

The 12-week breakdown

Number the calendar from week 1 (today) and back into it.

Week 1, scope and contractor selection

Walk the kitchen with two GCs, get two quotes. Confirm what is in scope and out of scope in writing.

Week 2, showroom visit and design

Cabinet line, door style, stone selection, tile selection, faucet, hardware. One sitting at our showroom is usually enough.

Week 3, plans, permits, deposits

Final layout drawing approved by you. 50 percent deposit on cabinets locks the order. Permit filings start.

Week 4, demo prep, dumpster permit

Empty the kitchen, set up the temporary cooking station, pull the dumpster permit, confirm parking with the neighbors.

Week 5, demo and rough plumbing

3 to 5 days demo, then plumber starts. Walls open.

Week 6, rough electrical, inspections

Electrician finishes rough. Plumbing and electrical rough inspections at end of week.

Week 7, drywall, paint, floor prep

Walls close, primed, painted. Floor underlayment goes in if needed.

Week 8, cabinets land and install

Cabinets arrive Monday, installed by Friday. Templater scheduled for early next week.

Week 9, stone template + tile floor

Stone goes to fab, 5 to 7 days. Floor tile installed mid-week.

Week 10, stone install + backsplash

Stone set Monday or Tuesday. Backsplash tile after stone is fully cured.

Week 11, finish plumbing + electrical, appliances

Faucet, disposal, dishwasher, hood, range. Final inspections.

Week 12, punch list and you move back in

Touch-up paint, hardware adjustments, cabinet door alignment. Final walkthrough.

12 weeks vs the 6-week sales pitch

Why the 6-week timeline you see in ads keeps slipping.

Phase12-week plan6-week pitch
Planning + ordering4 weeks1 week (rushed)
Build5 weeks4 weeks (no buffer)
Finish3 weeks1 week (no punch list)
Buffer for inspectionBuilt inNone
Realistic outcomeDone in 12Done in 9 to 11
  • The 6-week pitch becomes a 10-week reality, the 12-week plan stays at 12.
  • Customers who insist on 6 weeks often pay rush fees to make it work, which negates the savings.

How to use this plan

Print it, share it with the GC, agree on the dates, sign it.

  1. 1

    Mark every Friday as a milestone

    End of each week should have a verifiable deliverable, not just hours billed.

  2. 2

    Pay in tranches tied to milestones

    Don't pre-pay weeks 10 to 12 on day 1.

  3. 3

    Photos every Friday

    Make Friday photo updates a contractual requirement, not a favor.

What each week costs you (typical mid-range)

Approximate spend by week so you can plan cash flow.

WeekActivityApprox spend
3Cabinet deposit$8,000 to $12,000
4 to 7Demo + rough + drywall$10,000 to $15,000
8Cabinet balance + install$10,000 to $14,000
9 to 10Stone fab + install + tile$8,000 to $13,000
11Finish trades + appliances$5,000 to $9,000
12Punch list + final$2,000 to $4,000

Hold back 10 percent of the GC contract for week 12 punch list completion.

Mistakes to Avoid

  • Signing a 6-week schedule because it sounds good.
  • Not specifying the exact appliance models before week 3.
  • Letting the GC supply the cabinets and the stone, splitting suppliers gives you better pricing and accountability.
  • Skipping the permit filing because the GC offered to do it under the table.
  • Booking a vacation that lands on punch-list week.

FAQs

Can the plan be compressed to 10 weeks?+

Yes, by paying rush fees on cabinets (semi-custom in 4 weeks instead of 6), pre-ordering everything before week 1, and using a contractor with a dedicated crew.

What if I want to manage the project myself?+

Add 2 weeks to the schedule. Owner-managed projects spend more time coordinating trades, less time actually working.

Do you provide this schedule as a PDF?+

Yes, when you get an itemized quote from us, the schedule is page 2.

References

  • Internal job notes, Creative Home Decor, 1831 Utica Ave, Brooklyn, NY
  • NYC Department of Buildings renovation permits guidance, nyc.gov/dob
  • Remodeling Magazine 2025 Cost vs Value Report, New York metro
  • Kitchen Cabinet Manufacturers Association installation specs
  • Marble Institute of America natural stone care guidelines

Related services

kitchen remodel brooklynkitchen renovation costkitchen remodel timeline